mDOM assembly weekly meeting
mDOM assembly weekly meeting. Presenting progress reports, future plans, assembly issues, etc.
Announcements:
-
New paper travelers - please use and give feedback
-
Cabling - need to route camera, flashers, LED in specific spot between correct PMTs. Need to do this FIRST before adding other cables or it makes mainboard install hard. (See instructions.)
-
See new wall sign that shows where the cables are supposed to go, both top and bottom halves.
-
-
When entering into database, use “000000” for the glass hemisphere and scan in the support structure
-
Add penetrator cables to database when assembling holding structure
-
Add gel lot when pouring
-
Seal test works now!
Items Needed / Improvements:
-
Wrist anchorings when cabling - they get in the way
-
Can we make a tie bar from the copper ground? Copper wire? – Joining station needs this too. – Chris will get parts.
-
Schedule:
-
Gel pour next week Wed and Fri
-
Emmett leaving early on Friday
-
-
NO gel pour the week after that - focus on joining catch-up
-
Inspection and review coming early April - ideas for keeping lab clean and organized?