Minutes taken by Emmett:
This meeting will be at 9:45 am on Friday going forward
- Please send me your size for cloth garments if you don't have one hanging up right now (or if you prefer a size different from what's on your hangar)
- Please send me shoe size if you still need and want shoes
- We will start using ESD straps for mainboard and PMT install. Let Chris and I know if the straps interfere with your work and we will work on an alternate option.
- Items we need:
- PMT O-rings -- Chris will check packing list to see if we received more
- Tygon tubing, vacuum sealing tape - Emmett will add to spreadsheet
Our schedule for gel pour related-work each week will become fixed going forward, rather than updating it every week:
- Monday: Chris, Chase, Katelynn install 4x halves into holding structures and start evacuating
- Tuesday: Emmett confirms evacuation is ongoing. Can also load more gel if needed.
- Wednesday: Emmett, Grace start gel pour in morning. Chris, Chase finish in afternoon. Chris, Chase install 4x halves into holding structures and start evacuating.
- Thursday: Emmett confirms evacuation is ongoing. Can also load more gel if needed.
- Friday: Emmett start pour in morning. Chris, Chase finish in afternoon.
Joining schedule TBD, will be some combination of weekday afternoons. Need to join 4x mdoms per week